§ 157.210. Mainline natural gas facilities.
90 words·~1 min read·
/us/cfr/t18/s§ 157.210·A research copy — for the controlling text, always check the official state or federal source. Not legal advice.
Subject to the notice requirements of §§ 157.205(b) and 157.208(c), the certificate holder is authorized to acquire, construct, modify, replace, and operate natural gas mainline facilities, including compression and looping, that are not eligible facilities under § 157.202(b)(2)(i). The cost of a project may not exceed the cost limitation provided in column 2 of table 1 to § 157.208(d). The certificate holder must not segment projects in order to meet this cost limitation. \[Order 686, 71 FR 63693, Oct. 31, 2006, as amended at 89 FR 16684, Mar. 8, 2024\]
Connections1 cite this
Cited by 1 section
register
Citation graph
cites case law
§ 157.210
Mainline natural gas facilities.
Fed. Reg.×1
Cites 0Cited by 1 across 1 source