§ 158.31. Duration of authority to impose a PFC after project implementation.
122 words·~1 min read·
/us/cfr/t14/s§ 158.31·A research copy — for the controlling text, always check the official state or federal source. Not legal advice.
A public agency that has begun implementing an approved project may impose a PFC until—
(a)The charge expiration date is reached;
(b)The total PFC revenue collected plus interest earned thereon equals the allowable cost of the approved project;
(c)The authority to collect the PFC is terminated by the Administrator under subpart E of this part; or
(d)The public agency is determined by the Administrator to be in violation of 49 U.S.C. 47524 and 47526, and the authority to collect the PFC is terminated under that statute's implementing regulations under this title. [Docket 26385, 56 FR 24278, May 29, 1991, as amended by Amdt. 158-2, 65 FR 34542, May 30, 2000; Amdt. 158-4, 72 FR 28849, May 23, 2007]
Connectionstraces to 1
Traces to 1 document
Citation graph
cites case law
§ 158.31
Duration of authority to impose a PFC after project implementation.
Cites 1Cited by 0 across 0 sources