§ 305.8. Recipient-furnished equipment and materials.
138 words·~1 min read·
/us/cfr/t13/s§ 305.8·A research copy — for the controlling text, always check the official state or federal source. Not legal advice.
The Recipient may wish to incorporate into the Project equipment or materials that it will secure through its own efforts, subject to the following requirements:
(a)EDA must approve any use of Recipient-furnished equipment and materials. EDA may require that major equipment items be subject to a lien in favor of EDA and also may require a statement from the Recipient regarding expected useful life and salvage value of such equipment;
(b)EDA may require the Recipient to establish that the expense claimed for such equipment or materials is competitive with current local market costs; and
(c)Acquisition of Recipient-furnished equipment or materials under this section also is subject to the requirements of 2 CFR part 200. \[71 FR 56675, Sept. 27, 2006, as amended at 79 FR 76132, Dec. 19, 2014; 82 FR 57054, Dec. 1, 2017\]
Connections1 off-index
1 reference not yet in our index
- 2 CFR 200
Citation graph
cites case law
§ 305.8
Recipient-furnished equipment and materials.
Cite2 CFR 200
Cites 1Cited by 0 across 0 sources