## SEC. 405 SIMPLIFIED AND EXPEDITIOUS LICENSING PROCEDURES ###
(a)Establishment of Program The Commission shall establish, in such manner as the Commission deems appropriate, consistent with the applicable provisions of law, a program to use simple and expeditious licensing procedures under the Federal Power Act for small hydroelectric power projects in connection with existing dams. ###
(b)Prerequisites Before issuing any license under the Federal Power Act for the construction or operation of any small hydroelectric power project the Commission— ####
(1)shall assess the safety of existing structures in any proposed project (including possible consequences associated with failure of such structures), and ####
(2)shall provide an opportunity for consultation with the Council on Environmental Quality and the Environmental Protection Agency with respect to the environmental effects of such project. Nothing in this subsection exempts any such project from any requirement applicable to any such project under the National Environmental Policy Act of 1969, the Fish and Wildlife Coordination Act, the Endangered Species Act, or any other provision of Federal law. ###
(c)Fish and Wildlife Facilities The Commission shall encourage applicants for licenses for small hydroelectric power projects to make use of public funds and other assistance for the design and construction of fish and wildlife facilities which may be required in connection with any development of such project. ###
(d)Exemptions From Licensing Requirements in Certain Cases The Commission may in its discretion (by rule or order) grant an exemption in whole or in part from the requirements (including the licensing requirements) of part I of the Federal Power Act to small hydroelectric power projects having a proposed installed capacity of 10,000 kilowatts or less, on a case-by-case basis or on the basis of classes or categories of projects, subject to the same limitations (to ensure protection for fish and wildlife as well as other environmental concerns) as those which are set forth in subsections
(c)and
(d)of section 30 of the Federal Power Act with respect to determinations made and exemptions granted under subsection
(b)of such section 30; and subsections
(c)and
(d)of such section 30 shall apply with respect to actions taken and exemptions granted under this subsection. Except as specifically provided in this subsection, the granting of an exemption to a project under this subsection shall in no case have the effect of waiving or limiting the application (to such project) of the second sentence of subsection
(b)of this section. **[**[16 U.S.C. 2705](/us/usc/t16/s2705)**]**
Connectionstraces to 1
Citation graph
cites case law
Sec. 405
SIMPLIFIED AND EXPEDITIOUS LICENSING PROCEDURES
Cites 1Cited by 0 across 0 sources
★   the supreme law of the land   ★
Don't Tread on Me
E Pluribus Unum — out of many, one

"If you don't know your rights, you don't have any."

Marginalia · a citizen's law index
A research desk, not legal advice. Always read the cited source before relying on a summary.
Questions or an issue? support@self-law.org
disclaimerMarginalia is a research index, not a law firm. Nothing on this site is legal, tax, or financial advice and no attorney–client relationship is formed by using it. Statutes, regulations, and case law change; summaries, search results, AI output, and member posts may be incomplete, out of date, or wrong. Any interpretation drawn from material on this site should be validated by a licensed attorney in your jurisdiction before you act on it.