Sec. 2811. OBLIGATION AND EXECUTION OF DESIGN FUNDS FOR MILITARY CONSTRUCTION PROJECTS
264 words·~1 min read·
/statute-compilations/comps-18280/sec-2811A research copy — for the controlling text, always check the official state or federal source. Not legal advice.
## SEC. 2811 OBLIGATION AND EXECUTION OF DESIGN FUNDS FOR MILITARY CONSTRUCTION PROJECTS ###
(a)In General Not later than one year after amounts are appropriated for any fiscal year for the congressionally-directed design of a military construction project, the Secretary of Defense shall ensure that the construction agent responsible for such project enters into a contract pursuant to section 2807 of title 10, United States Code, for the obligation and execution of such amounts. ###
(b)Completion of Work If a military construction project designated pursuant to subsection
(a)has an estimated construction cost of less than $150,000,000, not less than 35 percent of the project design under a contract described in subsection
(a)shall be completed not later than 240 days after the date of the award of such contract. ###
(c)Notification If the Secretary determines that a construction agent who is responsible for a military construction project under subsection
(a)fails to satisfy the requirements of subsection
(a)or (b), the Secretary shall, not later than 30 days after the Secretary makes such determination and at the end of each ninety-day period thereafter until such military construction project reaches 35 percent design, submit to the congressional defense committees a notification that includes— ####
(1)a statement of whether the construction agent has exceeded the duration to— #####
(A)enter into a contract under subsection (a); or #####
(B)complete 35 percent project design under subsection (b); ####
(2)the reason for the delay in the satisfaction of such requirements; and ####
(3)the projected dates such requirements will be satisfied.