Sec. 3127. DEADLINES FOR COMMENCEMENT OF OPERATIONS OF CERTAIN ATOMIC ENERGY REPLACEMENT PROJECTS
252 words·~1 min read·
/statute-compilations/comps-17632/sec-3127A research copy — for the controlling text, always check the official state or federal source. Not legal advice.
## SEC. 3127 DEADLINES FOR COMMENCEMENT OF OPERATIONS OF CERTAIN ATOMIC ENERGY REPLACEMENT PROJECTS ###
(a)High Explosive Synthesis, Formulation, and Production Facility ####
(1)Deadline for commencement of operations Project 21-D-510, the High Explosive Synthesis, Formulation, and Production facility, shall commence operations by not later than December 31, 2034. ####
(2)Annual report #####
(A)In general The Administrator for Nuclear Security shall submit to the congressional defense committees, not later than February 1 of each year until the termination date specified in subparagraph (B), a report that includes a comprehensive estimate of the funds necessary, by year, to achieve the deadline specified in paragraph (1). #####
(B)Termination date The termination date specified in this subparagraph is the date on which the Administrator determines that the facility referred to in paragraph
(1)has commenced operations. ###
(b)Tritium Finishing Facility ####
(1)Deadline for commencement of operations Project 18-D-650, the Tritium Finishing Facility, shall commence operations by not later than December 31, 2036. ####
(2)Annual report #####
(A)In general The Administrator for Nuclear Security shall submit to the congressional defense committees, not later than February 1 of each year until the termination date specified in subparagraph (B), a report that includes a comprehensive estimate of the funds necessary, by year, to achieve the deadline specified in paragraph (1). #####
(B)Termination date The termination date specified in this subparagraph is the date on which the Administrator determines that the facility referred to in paragraph
(1)has commenced operations.