Sec. 8365. WOLF RIVER HARBOR, TENNESSEE
154 words·~1 min read·
/statute-compilations/comps-17475/sec-8365A research copy — for the controlling text, always check the official state or federal source. Not legal advice.
## SEC. 8365 WOLF RIVER HARBOR, TENNESSEE Beginning on the date of enactment of this Act, the project for navigation, Wolf River Harbor, Tennessee, authorized by section 202 of the National Industrial Recovery Act (48 Stat. 201; 49 Stat. 1034; 72 Stat. 308), is modified to reduce, in part, the authorized dimensions of the project, such that the remaining authorized dimensions are as follows: ####
(1)A 250-foot-wide, 9-foot-depth channel with a center line beginning at an approximate point of 35.139634, -90.062343 and extending approximately 1,300 feet to an approximate point of 35.142077, -90.059107. ####
(2)A 200-foot-wide, 9-foot-depth channel with a center line beginning at an approximate point of 35.142077, -90.059107 and extending approximately 1,800 feet to an approximate point of 35.1467861, -90.057003. ####
(3)A 250-foot-wide, 9-foot-depth channel with a center line beginning at an approximate point of 35.1467861, -90.057003 and extending approximately 5,550 feet to an approximate point of 35.160848, -90.050566.
Connectionstraces to 1
Traces to 1 document
statutes-at-large
2 references not yet in our index
- 48 Stat. 201
- 72 Stat. 308
Citation graph
cites case law
Cites 3Cited by 0 across 0 sources