Sec. 8155. CONTINUATION OF CONSTRUCTION

657 words·~3 min read·/statute-compilations/comps-17475/sec-8155

A research copy — for the controlling text, always check the official state or federal source. Not legal advice.

## SEC. 8155 CONTINUATION OF CONSTRUCTION **[**[33 U.S.C. 2280 note](/us/usc/t33/s2280)**]** ###
(a)Continuation of Construction ####
(1)In general Upon the transmittal of an initial notification pursuant to subsection (b)(1) with respect to a water resources development project, the Secretary shall not, solely on the basis of the maximum cost requirements under section 902 of the Water Resources Development Act of 1986 (33 U.S.C. 2280)— #####
(A)defer the initiation or continuation of construction of the water resources development project during the covered period; or #####
(B)terminate during or after the covered period, a contract for design or construction of the water resources development project that was entered into prior to or during the covered period. ####
(2)Resumption of construction The Secretary shall, upon the transmittal of an initial notification pursuant to subsection (b)(1) with respect to a water resources development project for which construction was deferred, during the period beginning on October 1, 2021, and ending on the date of enactment of this Act, because the cost of such project exceeded the maximum cost permitted under section 902 of the Water Resources Development Act of 1986 (33 U.S.C. 2280), resume construction of the project. ###
(b)Notification ####
(1)Initial notification Not later than 30 days after the Chief of Engineers makes a determination that a water resources development project exceeds, or is expected to exceed, the maximum cost of the project permitted under section 902 of the Water Resources Development Act of 1986 (33 U.S.C. 2280), the Chief of Engineers shall transmit a written notification concurrently to the Secretary and to the Committee on Environment and Public Works of the Senate and the Committee on Transportation and Infrastructure of the House of Representatives for each such determination. ####
(2)Supplemental notification Not later than 60 days after the Chief of Engineers transmits an initial notification required under paragraph (1), the Chief shall transmit concurrently to the Secretary and to the Committee on Environment and Public Works of the Senate and the Committee on Transportation and Infrastructure of the House of Representatives a supplemental notification that includes, based on information available to the Corps of Engineers on the date of the supplemental notification— #####
(A)an estimate of the expected increase in the cost of the project that is in excess of the authorized maximum cost for the project; #####
(B)a description of the reason for the increased cost of the project; and #####
(C)the expected timeline for submission of a post-authorization change report for the project in accordance with section 1132 of the Water Resources Development Act of 2016 (33 U.S.C. 2282e). ####
(3)Transmittal The notifications described in paragraphs
(1)and
(2)may not be delayed as a result of consideration being given to changes in policy or priority with respect to project consideration. ###
(c)Deferral of Construction After expiration of the covered period, the Secretary shall not enter into any new contract, or exercise any option in a contract, for construction of a water resources development project if the project exceeds the maximum cost of the project permitted under section 902 of the Water Resources Development Act of 1986 (33 U.S.C. 2280), until the date on which Congress authorizes an increase in the cost of the project. ###
(d)Statutory Construction Nothing in this section waives the obligation of the Secretary to submit to the Committee on Environment and Public Works of the Senate and the Committee on Transportation and Infrastructure of the House of Representatives a post-authorization change report recommending an increase in the authorized cost of a project if the project otherwise would exceed the maximum cost of the project permitted under section 902 of the Water Resources Development Act of 1986 (33 U.S.C. 2280). ###
(e)Definition of Covered Period In this section, the term “covered period” means the period beginning on the date of enactment of this Act and ending on December 31, 2024.
Connectionstraces to 2
Citation graph
cites case law
Sec. 8155
CONTINUATION OF CONSTRUCTION
Cites 2Cited by 0 across 0 sources
★   the supreme law of the land   ★
Don't Tread on Me
E Pluribus Unum — out of many, one

"If you don't know your rights, you don't have any."

Marginalia · a citizen's law index
A research desk, not legal advice. Always read the cited source before relying on a summary.
Questions or an issue? support@self-law.org
disclaimerMarginalia is a research index, not a law firm. Nothing on this site is legal, tax, or financial advice and no attorney–client relationship is formed by using it. Statutes, regulations, and case law change; summaries, search results, AI output, and member posts may be incomplete, out of date, or wrong. Any interpretation drawn from material on this site should be validated by a licensed attorney in your jurisdiction before you act on it.