Sec. 1069. MISCELLANEOUS HIGHWAY PROJECT AUTHORIZATIONS
1,640 words·~7 min read·
/statute-compilations/comps-1422/sec-1069A research copy — for the controlling text, always check the official state or federal source. Not legal advice.
## SEC. 1069 MISCELLANEOUS HIGHWAY PROJECT AUTHORIZATIONS ###
(a)Baltimore-Washington Parkway There is authorized to be appropriated $74,000,000 for renovation and reconstruction of the Baltimore-Washington Parkway in Prince Georges County, Maryland. The Federal share of the cost of such project shall be 100 percent. ###
(b)Exit 26 Bridge There is authorized to be appropriated $22,400,000 for construction of the Exit 26 Bridge in Schenectady County, New York. The Federal share of the cost of such project shall be 80 percent. ###
(c)Cumberland Gap Tunnel There are authorized to be appropriated such sums as may be necessary to complete construction of the Cumberland Gap Tunnel, Kentucky, including associated approaches and other necessary road work. The Federal share of the cost of such project shall be 100 percent. ###
(d)Riverside Expressway There is authorized to be appropriated $53,400,000 for construction of the Riverside Expressway, including bridges crossing the Monongahela River and Buffalo Creek, in the vicinity of Fairmont, West Virginia. The Federal share of the cost of such project shall be 80 percent. ###
(e)Busway There is authorized to be appropriated $39,500,000 for design and construction of an exclusive busway linking Pittsburgh and Pittsburgh Airport. The Federal share of such project shall be 80 percent. ###
(f)Exton Bypass There is authorized to be appropriated $11,004,000 for construction of the Exton Bypass, in Exton, Pennsylvania. The Federal share of such project shall be 80 percent. ###
(g)Pennsylvania Route 33 Extension There is authorized to be appropriated $5,400,000 for extension of Route 33 in Northampton County, Pennsylvania. The Federal share of such project shall be 80 percent. ###
(h)U.S. Route 202 There is authorized to be appropriated $4,500,000 for construction of U.S. Route 202. The Federal share of such project shall be 80 percent. ###
(i)Woodrow Wilson Bridge There is authorized to be appropriated $15,000,000 for rehabilitation of the Woodrow Wilson Bridge. The Federal share of such project shall be 100 percent. ###
(j)Warren Outerbelt Improvement, Warren, Ohio There is authorized to be appropriated $1,000,000 for design and construction of Warren Outerbelt improvements, Warren, Ohio. The Federal share of such project shall be 80 percent. ###
(k)Ohio State Route 46 Improvements There is authorized to be appropriated $2,000,000 for design and construction of Ohio State Route 46 improvements. The Federal share of such project shall be 80 percent. ###
(l)Ohio State Route 5 Improvements There is authorized to be appropriated $1,000,000 for design and construction of Ohio State Route 5 improvements. The Federal share of such project shall be 80 percent. ###
(m)U.S. Route 62 Improvements, Ohio There is authorized to be appropriated $1,000,000 for design and construction of U.S. Route 62 improvements, Ohio. The Federal share of such project shall be 80 percent. ###
(n)Ohio State Route 534 Improvements There is authorized to be appropriated $1,000,000 for design and construction of Ohio State Route 534 improvements. The Federal share of such project shall be 80 percent. ###
(o)Ohio State Route 45 Improvements There is authorized to be appropriated $1,000,000 for design and construction of Ohio State Route 45 improvements. The Federal share of such project shall be 80 percent. ###
(p)Route 120, Lock Haven, Pennsylvania There is authorized to be appropriated $4,000,000 for the widening of Route 120 and the removal of unstable rockfill area, Lock Haven, Pennsylvania. The Federal share of such project shall be 80 percent. ###
(q)Truss Bridge, Tioga River, Lawrenceville, Pennsylvania There is authorized to be appropriated $3,200,000 to replace the existing Truss Bridge across the Tioga River, in Lawrenceville, Pennsylvania. The Federal share of such project shall be 80 percent. ###
(r)U.S. Route 6, Bradford County, Pennsylvania There is authorized to be appropriated $3,000,000 for the widening of U.S. Route 6 (Wysox Narrows Road), in Bradford County, Pennsylvania. The Federal share of such project shall be 80 percent. ###
(s)Sebring/Mansfield Bypass, Pennsylvania There is authorized to be appropriated $4,800,000 for design and construction of the Sebring/Mansfield Bypass on U.S. 15, Pennsylvania. The Federal share of such project shall be 80 percent. ###
(t)I–5 Improvements The States of Oregon and Washington should give priority consideration to improvements on the I–5 Corridor. The Secretary shall give priority consideration to funding I–5 improvements in Oregon and Washington from section 118(c)(2) of title 23, United States Code, as amended by this Act. The Secretary shall give the highest priority to those Oregon projects identified in the State's transportation improvement plan, and funds provided pursuant to this provision shall not be subject to any limitation on obligations for Federal-aid highways and highway safety construction programs. ###
(u)Route 219 The Secretary shall designate Route 219 from the Maryland line to Buffalo, New York, as part of the National Highway System. ###
(v)Coalfields Expressway There is authorized to be appropriated such sums as may be necessary for design and construction of the project known as “Coalfields Expressway” from Beckley, West Virginia, to the West Virginia-Virginia State line, generally following the corridor defined by, but not necessarily limited to, Routes 54, 97, 10, 16, and 83, and from the West Virginia-Virginia State line generally following Route 83 to Pound, Virginia. The Federal share of such project shall be 80 percent. ###
(w)United States Route 119 There is authorized to be appropriated $70,000,000 for upgrading United States Route 119 to 4 lanes beginning west of Huddy, Kentucky. The Federal share of such project shall be 80 percent. ###
(x)Chambersburg, Pennsylvania Not later than 30 days after the date of the enactment of this Act, in Chambersburg, Pennsylvania, at both the intersection of Lincoln Way and Sixth Street and the intersection of Lincoln Way and Coldbrook Avenue, the Pennsylvania Department of Transportation shall include an exclusive pedestrian phase in the existing lighting sequence between the hours of 8:00 and 8:30 a.m. and between the hours of 2:45 and 3:45 p.m. on weekdays. ###
(y)Construction of and Improvements to the Appalachian Development Highway System There is authorized to be appropriated such sums as may be necessary for projects involving construction of, and improvements to, corridors of the Appalachian Development Highway System. Funds provided to carry out the provisions of this section are to remain available until expended. ###
(z)United States Route 52 in West Virginia ####
(1)There is authorized to be appropriated such sums as may be necessary for projects for the construction, renovation, and reconstruction of United States Route 52 in West Virginia. ####
(2)The Federal share payable on account of any such project shall be 80 percent of the cost thereof. ###
(aa)Route 219, New York ####
(1)For the purpose of projects to improve and upgrade Route 219 in New York, from Springeville to the Pennsylvania border Route 219 shall be considered as eligible for funding under the Appalachian Development Highway System. ####
(2)For purposes of paragraph
(1)there is authorized to be appropriated such sums as may be necessary. The Federal share payable on account of such project shall be 80 percent of the cost thereof. ###
(bb)Routes 5 and 92 Congestion Management Project There is authorized to be appropriated $20,000,000 to carry out a project to relieve congestion in the vicinity of the intersection of routes 5 and 92 in the Towns of Manlius, New York, and Dewitt, New York. ###
(cc)Rochester Advanced Traffic Management System There is authorized to be appropriated $15,000,000 to implement an integrated advanced traffic management/advanced driver information system in the city of Rochester, New York. ###
(dd)Rensselaer Access Project There is authorized to be appropriated $35,000,000 to construct a new interchange (Exit 8) on Interstate Route 90, which includes an access-controlled roadway, in Rensselaer County, New York. ###
(ee)Gowanus Expressway Corridor Improvements There is authorized to be appropriated $200,000,000 to carry out improvements to the Gowanus Expressway Corridor in Brooklyn, New York. In carrying out such improvements, the State of New York shall consider the economic and social impacts of the project on the neighboring community. ###
(ff)I–287 Cross Westchester Expressway High Occupancy Vehicle Lane Project There is authorized to be appropriated $200,000,000 to construct High Occupancy Vehicle Lanes on the Cross Westchester Expressway in Westchester County, New York. ###
(gg)Intermodal Facilities, New York ####
(1)Authorization of appropriations There is authorized to be appropriated to carry out this subsection $150,000,000 for fiscal years beginning after September 30, 1995, for— #####
(A)design and construction of the Whitehall Street Ferry Terminals in New York, New York; #####
(B)completion of construction of the Oak Point Link in the Harlem River in New York, New York; #####
(C)engineering, design, and construction activities to permit the James A. Farley Post Office in New York, New York, to be used as an intermodal transportation facility and commercial center; and #####
(D)necessary improvements to and redevelopment of Pennsylvania Station and associated service buildings in New York, New York. Such sums shall remain available until expended. ####
(2)Allocation of funds Of the amounts made available under paragraph (1)— #####
(A)not to exceed $50,000,000 may be used to carry out paragraph (1)(A); and #####
(B)not to exceed $10,000,000 may be used to carry out paragraph (1)(B). ####
(3)Pennsylvania station redevelopment corporation board of directors In furtherance of the redevelopment of the James A. Farley Post Office in New York, New York, into an intermodal transportation facility and commercial center, the Secretary, the Administrator of the Federal Railroad Administration, or their designees are authorized to serve as ex officio members of the Board of Directors of the Pennsylvania Station Redevelopment Corporation. ###
(hh)Operational Improvements, Franklin Delano Roosevelt Drive There is authorized to be appropriated $50,000,000 to carry out operational and safety improvements to the Franklin Delano Roosevelt Drive in New York City, New York.