Sec. 508. SAN JUAN-CHAMA PROJECT CONTRACTS
325 words·~1 min read·
/statute-compilations/comps-13809/sec-508A research copy — for the controlling text, always check the official state or federal source. Not legal advice.
## SEC. 508 SAN JUAN-CHAMA PROJECT CONTRACTS ###
(a)In general Contracts issued under this section shall be in accordance with this title and the Settlement Agreement. ###
(b)Contracts for San Juan-Chama Project Water ####
(1)In general The Secretary shall enter into 3 repayment contracts within a reasonable period after the date of enactment of this Act, for the delivery of San Juan-Chama Project water in the following amounts: #####
(A)2,215 acre-feet/annum to the Pueblo. #####
(B)366 acre-feet/annum to the Town of Taos. #####
(C)40 acre-feet/annum to the El Prado Water and Sanitation District. ####
(2)Requirements Each such contract shall provide that if the conditions precedent set forth in section 509(f)(2) have not been fulfilled by March 31, 2017, the contract shall expire on that date. ####
(3)Applicable law Public Law 87-483 (76 Stat. 97) applies to the contracts entered into under paragraph
(1)and no preference shall be applied as a result of section 504(a) with regard to the delivery or distribution of San Juan-Chama Project water or the management or operation of the San Juan-Chama Project. ###
(c)Waiver With respect to the contract authorized and required by subsection (b)(1)(A) and notwithstanding the provisions of Public Law 87-483 (76 Stat. 96) or any other provision of law— ####
(1)the Secretary shall waive the entirety of the Pueblo’s share of the construction costs, both principal and the interest, for the San Juan-Chama Project and pursuant to that waiver, the Pueblo’s share of all construction costs for the San Juan-Chama Project, inclusive of both principal and interest shall be nonreimbursable; and ####
(2)the Secretary’s waiver of the Pueblo’s share of the construction costs for the San Juan-Chama Project will not result in an increase in the pro rata shares of other San Juan-Chama Project water contractors, but such costs shall be absorbed by the United States Treasury or otherwise appropriated to the Department of the Interior.
Connectionstraces to 1
Traces to 1 document
statutes-at-large
2 references not yet in our index
- Pub. L. 87-483
- 76 Stat. 97
Citation graph
cites case law
Cites 3Cited by 0 across 0 sources