Sec. 206. USE OF CONTINUING CONTRACTS FOR CONSTRUCTION OF CERTAIN PROJECTS
142 words·~1 min read·
/statute-compilations/comps-10924/sec-206A research copy — for the controlling text, always check the official state or federal source. Not legal advice.
## SEC. 206 USE OF CONTINUING CONTRACTS FOR CONSTRUCTION OF CERTAIN PROJECTS **[**[33 U.S.C. 2331](/us/usc/t33/s2331)**]** ###
(a)In General Notwithstanding any other provision of law, the Secretary shall not implement a fully allocated funding policy with respect to a water resource project if initiation of construction has occurred but sufficient funds are not available to complete the project. ###
(b)Continuing Contracts The Secretary shall enter into a continuing contract for a project described in subsection (a). ###
(c)Initiation of Construction Clarified For the purposes of this section, initiation of construction for a project occurs on the date of enactment of an Act that appropriates funds for the project from 1 of the following appropriation accounts: ####
(1)Construction, General. ####
(2)Operation and Maintenance, General. ####
(3)Flood Control, Mississippi River and Tributaries. * * * * * * *
Connectionstraces to 1
Traces to 1 document
Citation graph
cites case law
Sec. 206
USE OF CONTINUING CONTRACTS FOR CONSTRUCTION OF CERTAIN PROJECTS
Cites 1Cited by 0 across 0 sources