Sec. 1911. APPROVAL AND FUNDING FOR CERTAIN CONSTRUCTION PROJECTS
168 words·~1 min read·
/statute-compilations/comps-10915/sec-1911A research copy — for the controlling text, always check the official state or federal source. Not legal advice.
## SEC. 1911 APPROVAL AND FUNDING FOR CERTAIN CONSTRUCTION PROJECTS ###
(a)Project Approval If the Secretary finds that the project number STP–189–1(15)CT 3 in Gwinnett County, Georgia, was not listed in the current regional transportation plan because of a clerical error, such failure to be listed shall not be a basis for not approving the project. The Secretary shall make a final decision on the approval of the project within 30 days after the date of receipt by the Secretary of a construction authorization request from the department of transportation for the State of Georgia. ###
(b)Conformity Determination ####
(1)In general Approval, funding, and implementation of the project referred to in subsection
(a)shall not be subject to the requirements of part 93 of title 40, Code of Federal Regulations (or successor regulations). ####