## SEC. 1839 TRANSMISSION SYSTEM MONITORING Within 6 months after the date of enactment of this Act, the Secretary and the Federal Energy Regulatory Commission shall study and report to Congress on the steps which must be taken to establish a system to make available to all transmission system owners and Regional Transmission Organizations (as defined in the Federal Power Act) within the Eastern and Western Interconnections real-time information on the functional status of all transmission lines within such Interconnections.
In such study, the Commission shall assess technical means for implementing such transmission information system and identify the steps the Commission or Congress must take to require the implementation of such system.