Sec. 6. PROMOTING HYDROPOWER DEVELOPMENT AT NONPOWERED DAMS AND CLOSED LOOP PUMPED STORAGE PROJECTS

573 words·~3 min read·/statute-compilations/comps-10542/sec-6

A research copy — for the controlling text, always check the official state or federal source. Not legal advice.

## SEC. 6 PROMOTING HYDROPOWER DEVELOPMENT AT NONPOWERED DAMS AND CLOSED LOOP PUMPED STORAGE PROJECTS **[**[16 U.S.C. 797 note](/us/usc/t16/s797)**]** ###
(a)In General To improve the regulatory process and reduce delays and costs for hydropower development at nonpowered dams and closed loop pumped storage projects, the Federal Energy Regulatory Commission (referred to in this section as the “Commission”) shall investigate the feasibility of the issuance of a license for hydropower development at nonpowered dams and closed loop pumped storage projects in a 2-year period (referred to in this section as a “2-year process”). Such a 2-year process shall include any prefiling licensing process of the Commission. ###
(b)Workshops and Pilots The Commission shall— ####
(1)not later than 60 days after the date of enactment of this Act, hold an initial workshop to solicit public comment and recommendations on how to implement a 2-year process; ####
(2)develop criteria for identifying projects featuring hydropower development at nonpowered dams and closed loop pumped storage projects that may be appropriate for licensing within a 2-year process; ####
(3)not later than 180 days after the date of enactment of this Act, develop and implement pilot projects to test a 2-year process, if practicable; and ####
(4)not later than 3 years after the date of implementation of the final pilot project testing a 2-year process, hold a final workshop to solicit public comment on the effectiveness of each tested 2-year process. ###
(c)Memorandum of Understanding The Commission shall, to the extent practicable, enter into a memorandum of understanding with any applicable Federal or State agency to implement a pilot project described in subsection (b). ###
(d)Reports ####
(1)Pilot projects not implemented If the Commission determines that no pilot project described in subsection
(b)is practicable because no 2-year process is practicable, not later than 240 days after the date of enactment of this Act, the Commission shall submit to the Committee on Energy and Commerce of the House of Representatives and the Committee on Energy and Natural Resources of the Senate a report that— #####
(A)describes the public comments received as part of the initial workshop held under subsection (b)(1); and #####
(B)identifies the process, legal, environmental, economic, and other issues that justify the determination of the Commission that no 2-year process is practicable, with recommendations on how Congress may address or remedy the identified issues. ####
(2)Pilot projects implemented If the Commission develops and implements pilot projects involving a 2-year process, not later than 60 days after the date of completion of the final workshop held under subsection (b)(4), the Commission shall submit to the Committee on Energy and Commerce of the House of Representatives and the Committee on Energy and Natural Resources of the Senate a report that— #####
(A)describes the outcomes of the pilot projects; #####
(B)describes the public comments from the final workshop on the effectiveness of each tested 2-year process; and #####
(C)######
(i)outlines how the Commission will adopt policies under existing law (including regulations) that result in a 2-year process for appropriate projects; ######
(ii)outlines how the Commission will issue new regulations to adopt a 2-year process for appropriate projects; or ######
(iii)identifies the process, legal, environmental, economic, and other issues that justify a determination of the Commission that no 2-year process is practicable, with recommendations on how Congress may address or remedy the identified issues.
Connectionstraces to 1
Traces to 1 document
Citation graph
cites case law
Sec. 6
PROMOTING HYDROPOWER DEVELOPMENT AT NONPOWERED DAMS AND CLOSED LOOP PUMPED STORAGE PROJECTS
Cites 1Cited by 0 across 0 sources
★   the supreme law of the land   ★
Don't Tread on Me
E Pluribus Unum — out of many, one

"If you don't know your rights, you don't have any."

Marginalia · a citizen's law index
A research desk, not legal advice. Always read the cited source before relying on a summary.
Questions or an issue? support@self-law.org
disclaimerMarginalia is a research index, not a law firm. Nothing on this site is legal, tax, or financial advice and no attorney–client relationship is formed by using it. Statutes, regulations, and case law change; summaries, search results, AI output, and member posts may be incomplete, out of date, or wrong. Any interpretation drawn from material on this site should be validated by a licensed attorney in your jurisdiction before you act on it.