Sec. 2808. AUTHORITY TO USE OPERATION AND MAINTENANCE FUNDS FOR CERTAIN CONSTRUCTION PROJECTS OUTSIDE THE UNITED STATES
762 words·~3 min read·
/statute-compilations/comps-10407/sec-2808A research copy — for the controlling text, always check the official state or federal source. Not legal advice.
## SEC. 2808 AUTHORITY TO USE OPERATION AND MAINTENANCE FUNDS FOR CERTAIN CONSTRUCTION PROJECTS OUTSIDE THE UNITED STATES ###
(a)In General The Secretary of Defense may obligate appropriated funds available for operation and maintenance to carry out a construction project outside the United States that the Secretary determines meets each of the following conditions: ####
(1)The construction is necessary to meet urgent military operational requirements of a temporary nature involving the use of the Armed Forces in support of a declaration of war, the declaration by the President of a national emergency under section 201 of the National Emergencies Act (50 U.S.C. 1621), or a contingency operation. ####
(2)The construction is not carried out at a military installation where the United States is reasonably expected to have a long-term presence. ####
(3)The United States has no intention of using the construction after the operational requirements have been satisfied. ####
(4)The level of construction is the minimum necessary to meet the temporary operational requirements. ###
(b)Notification of Obligation of Funds Before using appropriated funds available for operation and maintenance to carry out a construction project outside the United States that has an estimated cost in excess of the amounts authorized for unspecified minor military construction projects under section 2805(c) of title 10, United States Code, the Secretary of Defense shall submit to the congressional committees specified in subsection
(d)a notice regarding the construction project. The project may be carried out only after the end of the 14-day period beginning on the date the notice is received by the committees, including when a copy of the notification is provided in an electronic medium pursuant to section 480 of title 10, United States Code. The notice shall include the following: ####
(1)Certification that the conditions specified in subsection
(a)are satisfied with regard to the construction project. ####
(2)A description of the purpose for which appropriated funds available for operation and maintenance are being obligated. ####
(3)All relevant documentation detailing the construction project. ####
(4)An estimate of the total amount obligated for the construction. ###
(c)Annual Limitation on Use of Authority ####
(1)The total cost of the construction projects carried out under the authority of this section using, in whole or in part, appropriated funds available for operation and maintenance shall not exceed $50,000,000 during each of the following periods: #####
(A)The period beginning October 1, 2021, and ending on the earlier of December 31, 2022, or the date of the enactment of an Act authorizing funds for military activities of the Department of Defense for fiscal year 2023. #####
(B)The period beginning October 1, 2022, and ending on the earlier of December 31, 2023, or the date of the enactment of an Act authorizing funds for military activities of the Department of Defense for fiscal year 2024. ####
(2)Notwithstanding paragraph (1), the Secretary of Defense may authorize the obligation under this section of not more than an additional $10,000,000 of appropriated funds available for operation and maintenance for a fiscal year if the Secretary determines that the additional funds are needed for costs associated with contract closeouts. ####
(3)The total amount of operation and maintenance funds used for a single construction project carried out under the authority of this section shall not exceed $15,000,000. The Secretary of Defense may waive this limitation on a project-by-project basis. This waiver authority may not be delegated. ###
(d)Congressional Committees The congressional committees referred to in this section are the following: ####
(1)The Committee on Armed Services and the Subcommittee on Defense and the Subcommittee on Military Construction, Veterans Affairs, and Related Agencies of the Committee on Appropriations of the Senate. ####
(2)The Committee on Armed Services and the Subcommittee on Defense and the Subcommittee on Military Construction, Veterans Affairs, and Related Agencies of the Committee on Appropriations of the House of Representatives. ###
(e)Effect of Failure to Submit Project Notifications If the advance notice of the proposed obligation of the funds for a construction project required by subsection
(b)is not submitted to the congressional committees specified in subsection
(d)by the required date, appropriated funds available for operation and maintenance may not be obligated or expended after that date under the authority of this section to carry out construction projects outside the United States until the date on which the notice is finally submitted. * * * * * * * ## Subtitle C Base Closure and Realignment * * * * * * *
Connectionstraces to 1