Sec. 846. REQUIREMENTS FOR RISK ASSESSMENTS RELATED TO CONTRACTOR PERFORMANCE

812 words·~4 min read·/statute-compilations/comps-10359/sec-846

A research copy — for the controlling text, always check the official state or federal source. Not legal advice.

## SEC. 846 REQUIREMENTS FOR RISK ASSESSMENTS RELATED TO CONTRACTOR PERFORMANCE **[**[10 U.S.C. 2302 note](/us/usc/t10/s2302)**]** ###
(a)Risk Assessments for Contractor Performance in Operational or Contingency Plans The Secretary of Defense shall require that a risk assessment on reliance on contractors be included in operational or contingency plans developed by a commander of a combatant command in executing the responsibilities prescribed in section 164 of title 10, United States Code. Such risk assessments shall address, at a minimum, the potential risks listed in subsection (c). ###
(b)Comprehensive Risk Assessments and Mitigation Plans for Contractor Performance in Support of Overseas Contingency Operations ####
(1)In general Subject to paragraphs
(2)and (3), not later than six months after the commencement or designation of a contingency operation outside the United States that includes or is expected to include combat operations, the head of each covered agency shall perform a comprehensive risk assessment and develop a risk mitigation plan for operational and political risks associated with contractor performance of critical functions in support of the operation for such covered agency. ####
(2)Exceptions Except as provided in paragraph (3), a risk assessment and risk mitigation plan shall not be required under paragraph
(1)for an overseas contingency operation if— #####
(A)the operation is not expected to continue for more than one year; and #####
(B)the total amount of obligations for contracts for support of the operation for the covered agency is not expected to exceed $250,000,000. ####
(3)Termination of exceptions Notwithstanding paragraph (2), the head of a covered agency shall perform a risk assessment and develop a risk mitigation plan under paragraph
(1)for an overseas contingency operation with regard to which a risk assessment and risk mitigation plan has not previously been performed under paragraph
(1)not later than 60 days after the date on which— #####
(A)the operation has continued for more than one year; or #####
(B)the total amount of obligations for contracts for support of the operation for the covered agency exceeds $250,000,000. ###
(c)Comprehensive Risk Assessments A comprehensive risk assessment under subsection
(b)shall consider, at a minimum, risks relating to the following: ####
(1)The goals and objectives of the operation (such as risks from contractor behavior or performance that may injure innocent members of the local population or offend their sensibilities). ####
(2)The continuity of the operation (such as risks from contractors refusing to perform or being unable to perform when there may be no timely replacements available). ####
(3)The safety of military and civilian personnel of the United States if the presence or performance of contractor personnel creates unsafe conditions or invites attack. ####
(4)The safety of contractor personnel employed by the covered agency. ####
(5)The managerial control of the Government over the operation (such as risks from over-reliance on contractors to monitor other contractors or inadequate means for Government personnel to monitor contractor performance). ####
(6)The critical organic or core capabilities of the Government, including critical knowledge or institutional memory of key operations areas and subject-matter expertise. ####
(7)The ability of the Government to control costs, avoid organizational or personal conflicts of interest, and minimize waste, fraud, and abuse. ###
(d)Risk Mitigation Plans A risk mitigation plan under subsection
(b)shall include, at a minimum, the following: ####
(1)For each high-risk area identified in the comprehensive risk assessment for the operation performed under subsection (b)— #####
(A)specific actions to mitigate or reduce such risk, including the development of alternative capabilities to reduce reliance on contractor performance of critical functions; #####
(B)measurable milestones for the implementation of planned risk mitigation or risk reduction measures; and #####
(C)a process for monitoring, measuring, and documenting progress in mitigating or reducing risk. ####
(2)A continuing process for identifying and addressing new and changed risks arising in the course of the operation, including the periodic reassessment of risks and the development of appropriate risk mitigation or reduction plans for any new or changed high-risk area identified. ###
(e)Critical Functions For purposes of this section, critical functions include, at a minimum, the following: ####
(1)Private security functions, as that term is defined in section 864(a)(6) of the National Defense Authorization Act for Fiscal Year 2008 (10 U.S.C. 2302 note). ####
(2)Training and advising Government personnel, including military and security personnel, of a host nation. ####
(3)Conducting intelligence or information operations. ####
(4)Any other functions that are closely associated with inherently governmental functions, including the functions set forth in section 7.503(d) of the Federal Acquisition Regulation. ####
(5)Any other functions that are deemed critical to the success of the operation. ###
(f)Covered Agency In this section, the term “covered agency” means the Department of Defense, the Department of State, and the United States Agency for International Development.
Connectionstraces to 1
Citation graph
cites case law
Sec. 846
REQUIREMENTS FOR RISK ASSESSMENTS RELATED TO CONTRACTOR PERFORMANCE
Cites 1Cited by 0 across 0 sources
★   the supreme law of the land   ★
Don't Tread on Me
E Pluribus Unum — out of many, one

"If you don't know your rights, you don't have any."

Marginalia · a citizen's law index
A research desk, not legal advice. Always read the cited source before relying on a summary.
Questions or an issue? support@self-law.org
disclaimerMarginalia is a research index, not a law firm. Nothing on this site is legal, tax, or financial advice and no attorney–client relationship is formed by using it. Statutes, regulations, and case law change; summaries, search results, AI output, and member posts may be incomplete, out of date, or wrong. Any interpretation drawn from material on this site should be validated by a licensed attorney in your jurisdiction before you act on it.