Sec. 5062. NASA MID-RANGE PROCUREMENT TEST PROGRAM
415 words·~2 min read·
/statute-compilations/comps-1008/sec-5062A research copy — for the controlling text, always check the official state or federal source. Not legal advice.
## SEC. 5062 NASA MID-RANGE PROCUREMENT TEST PROGRAM **[**[42 U.S.C. 2473 note](/us/usc/t42/s2473)**]** ###
(a)In General The Administrator of the National Aeronautics and Space Administration (in this section referred to as the “Administrator”) may conduct a test of alternative notice and publication requirements for procurements conducted by the National Aeronautics and Space Administration. To the extent consistent with this section, such program shall be conducted consistent with section 15 of the Office of Federal Procurement Policy Act (41 U.S.C. 413).5 5Section 15 of the Office of Federal Procurement Policy Act, referred to in subsection (a), is set forth beginning on page 574. ###
(b)Applicability The test conducted under subsection
(a)shall apply to acquisitions with an estimated annual total obligation of funds of $500,000 or less. ###
(c)Limitation on Total Cost The total estimated life-cycle cost to the Federal Government for the test conducted under subsection
(a)may not exceed $100,000,000. ###
(d)Waiver of Procurement Regulations ####
(1)In conducting the test under this section, the Administrator, with the approval of the Administrator for Federal Procurement Policy, may waive— #####
(A)any provision of the Federal Acquisition Regulation that is not required by statute; and #####
(B)any provision of the Federal Acquisition Regulation that is required by a provision of law described in paragraph (2), the waiver of which the Administrator determines in writing to be necessary to conduct the test. ####
(2)The provisions of law referred to in paragraph
(1)are as follows: #####
(A)Subsections (e), (f), and
(g)of section 8 of the Small Business Act (15 U.S.C. 637). #####
(B)Section 18 of the Office of Federal Procurement Policy Act (41 U.S.C. 416). ###
(e)Report Not later than 6 months after completion of the test conducted under subsection (a), the Comptroller General shall submit to Congress a report for the test setting forth in detail the results of the test, including such recommendations as the Comptroller General considers appropriate. ###
(f)Expiration of Authority The authority to conduct the test under subsection
(a)and to award contracts under such test shall expire 4 years after the date of the enactment of this Act. Contracts entered into before such authority expires shall remain in effect, notwithstanding the expiration of the authority to conduct the test under this section. ###
(g)Rule of Construction Nothing in this section shall be construed as authorizing the appropriation or obligation of funds for the test conducted pursuant to subsection (a).
Connectionstraces to 1
Traces to 1 document
U.S. Code
3 references not yet in our index
- 42 USC 2473
- 41 USC 413
- 41 USC 416
Citation graph
cites case law
Sec. 5062
NASA MID-RANGE PROCUREMENT TEST PROGRAM
Cite42 USC 2473
Cite41 USC 413
Cite41 USC 416
Cites 4Cited by 0 across 0 sources