49-41B-5. Notification of intent to apply for permit required before filing application--Time--Prefiling conference if applicant requests.
60 words·~1 min read·
/sd/title-49/chapter-49-41/49-41b-5A research copy — for the controlling text, always check the official state or federal source. Not legal advice.
A notification of intent to apply for a permit for construction of an energy conversion facility or AC/DC conversion facility shall be filed with the Public Utilities Commission at least six months before filing an application as required in § 49-41B-11 . A prefiling conference may be requested by the applicant and such request shall be granted by the commission.