49-41B-25. Permit for wind or solar energy facility--Time for complete findings by commission--Notice of decision.

104 words·~1 min read·/sd/title-49/chapter-49-41/49-41b-25·

A research copy — for the controlling text, always check the official state or federal source. Not legal advice.

Within nine months of receipt of the initial application for a permit for the construction of a wind energy facility or solar energy facility, the commission shall make complete findings, and render a decision, regarding whether a permit should be granted, denied, or granted upon such terms, conditions, or modifications of the construction, operation, or maintenance as the commission determines are appropriate. In the decision, the commission shall find that the construction of the facility meets all requirements of this chapter. Notice of the commission's decision shall be given to the applicant and to parties to the hearing within ten days following the decision.
★   the supreme law of the land   ★
Don't Tread on Me
E Pluribus Unum — out of many, one

"If you don't know your rights, you don't have any."

Marginalia · a citizen's law index
A research desk, not legal advice. Always read the cited source before relying on a summary.
Questions or an issue? support@self-law.org
disclaimerMarginalia is a research index, not a law firm. Nothing on this site is legal, tax, or financial advice and no attorney–client relationship is formed by using it. Statutes, regulations, and case law change; summaries, search results, AI output, and member posts may be incomplete, out of date, or wrong. Any interpretation drawn from material on this site should be validated by a licensed attorney in your jurisdiction before you act on it.