49-41B-24. Permit for energy conversion facilities, AC/DC conversion facilities, or transmission facilities--Complete findings by commission required within year of application.
62 words·~1 min read·
/sd/title-49/chapter-49-41/49-41b-24·A research copy — for the controlling text, always check the official state or federal source. Not legal advice.
Within twelve months of receipt of the initial application for a permit for the construction of energy conversion facilities, AC/DC conversion facilities, or transmission facilities, the commission shall make complete findings in rendering a decision regarding whether a permit should be granted, denied, or granted upon such terms, conditions or modifications of the construction, operation, or maintenance as the commission deems appropriate.