Notices. DEPARTMENT OF ENERGY
196 words·~1 min read·
/register/2018/12/28/2018-28255A research copy — for the controlling text, always check the official state or federal source. Not legal advice.
BILLING CODE 6717-01-P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Docket No. EL19-24-000] Exelon Generation Company, LLC; Notice of Institution of Section 206 Proceeding and Refund Effective Date On December 20, 2018, the Commission issued an order in Docket No. EL19-24-000, pursuant to section 206 of the Federal Power Act (FPA), 16 U.S.C. 824e (2012), instituting an investigation into the continued justness and reasonableness of Exelon Generation Company, LLC's rate for providing Reactive Supply and Voltage Control Service. *Exelon Generation Company, LLC,* 165 FERC 61,245 (2018).
The refund effective date in Docket No. EL19-24-000, established pursuant to section 206(b) of the FPA, will be the date of publication of this notice in the **Federal Register** . Any interested person desiring to be heard in Docket No. EL19-24-000 must file a notice of intervention or motion to intervene, as appropriate, with the Federal Energy Regulatory Commission, 888 First Street NE, Washington, DC 20426, in accordance with Rule 214 of the Commission's Rules of Practice and Procedure, 18 CFR 385.214, within 21 days of the date of issuance of the order.
Dated: December 20, 2018. Nathaniel J. Davis, Sr., Deputy Secretary. [FR Doc. 2018-28255 Filed 12-27-18; 8:45 am]
Connectionstraces to 2
Citation graph
cites case law
Cites 2Cited by 0 across 0 sources