Rules and Regulations. Notice of temporary deviation from regulations
/register/2011/11/23/2011-30187·A research copy — for the controlling text, always check the official state or federal source. Not legal advice.
Agency: Coast Guard, DHS
Action: Notice of temporary deviation from regulations
Citation: FR Doc. 2011-30187 · Docket No. USCG-2011-1050 · 33 CFR 117
Summary
The Commander, First Coast Guard District, has issued a temporary deviation from the regulation governing the operation of the new Chelsea Street Bridge across the Chelsea River, mile 1.2, between Chelsea and East Boston, Massachusetts. The recently installed new vertical lift bridge span will undergo testing for three weeks. This deviation requires a four hour advance notice for bridge openings during the lift span test period.
Dates
This deviation is effective from 7 a.m. on November 12, 2011 through 11 a.m. on December 3, 2011.
Supplementary Information
The Chelsea Street Bridge, across the Chelsea River, mile 1.2, between Chelsea and East Boston, Massachusetts, has a vertical clearance in the closed position of 7 feet above mean high water and 17 feet above mean low water, and 175 feet above mean high water in the full open position. The bridge opens on signal at all times as required by 33 CFR 117.593. The waterway is transited predominantly by commercial operators delivering petroleum products to facilities located upstream from the new bridge. The lift span at the new bridge will be operated by the contractor, J.F. White Company, for testing from 7 a.m. on November 12, 2011 through 11 a.m. on December 3, 2011. At least a four hour advance notice shall be required for bridge openings during the above test period. Requests to open the bridge may be made by calling J.F. White Company at (617) 590-1286 or (617) 799-2913 or by VHF FM marine radio channel 13 and 16. The waterway users and upstream oil facilities, were all advised regarding the four hour advance notice requirement. No objections were received. In accordance with 33 CFR 117.35(e), the bridge must return to its regular operating schedule immediately at the end of the designated time period. This deviation from the operating regulations is authorized under 33 CFR 117.35. Dated: November 10, 2011. Gary Kassof, Bridge Program Manager, First Coast Guard District. [FR Doc. 2011-30187 Filed 11-22-11; 8:45 am]
Connectionstraces to 2
- 33 CFR 117