Rules and Regulations. Proposed rule with request for comments
/register/2003/09/15/03-23341·A research copy — for the controlling text, always check the official state or federal source. Not legal advice.
Agency: Department of Defense (DoD)
Action: Proposed rule with request for comments
Citation: FR Doc. 03-23341 · DFARS Case 2002-D032 · 48 CFR 246
Summary
DoD is proposing to amend the Defense Federal Acquisition Regulation Supplement (DFARS) to eliminate Government source inspection requirements for contracts or delivery orders valued below $250,000, unless certain conditions exist. This change will permit DoD contract administration offices to devote more resources to high-risk contracts.
Dates
DoD will consider all comments received by November 14, 2003.
Supplementary Information
A. Background This proposed rule adds policy at DFARS 246.402 and 246.404 to eliminate requirements for Government quality assurance at source on contracts or delivery orders valued below $250,000, unless (1) mandated by DoD regulation, (2) required by a memorandum of agreement between the acquiring department or agency and the contract administration agency, or (3) the contracting officer determines that certain conditions exist. The objective is to focus limited DoD contract management resources on high-risk areas, while providing flexibility for exceptions where needed. This rule was not subject to Office of Management and Budget review under Executive Order 12866, dated September 30, 1993. B. Regulatory Flexibility Act DoD does not expect this rule to have a significant economic impact on a substantial number of small entities within the meaning of the Regulatory Flexibility Act, 5 U.S.C. 601, et seq. , because the DFARS changes in this rule primarily affect the allocation of Government resources to contract quality assurance functions. Therefore, DoD has not performed an initial regulatory flexibility analysis. DoD invites comments from small businesses and other interested parties. DoD also will consider comments from small entities concerning the affected DFARS subpart in accordance with 5 U.S.C. 610. Such comments should be submitted separately and should cite DFARS Case 2002-D032. C. Paperwork Reduction Act The Paperwork Reduction Act does not apply because the rule does not impose any information collection requirements that require the approval of the Office of Management and Budget under 44 U.S.C. 3501, et seq. List of Subjects in 48 CFR Part 246 Government procurement. Michele P. Peterson, Executive Editor, Defense Acquisition Regulations Council. Therefore, DoD proposes to amend 48 CFR Part 246 as follows: 1. The authority citation for 48 CFR Part 246 continues to read as follows: Authority: 41 U.S.C. 421 and 48 CFR Chapter 1. PART 246—QUALITY ASSURANCE 2. Section 246.402 is added to read as follows: 246.402 Government contract quality assurance at source. Do not require Government contract quality assurance at source for contracts or delivery orders valued below $250,000, unless— (1) Mandated by DoD regulation; (2) Required by a memorandum of agreement between the acquiring department or agency and the contract administration agency; or (3) The contracting officer determines that— (i) Contract technical requirements are significant ( e.g. , the technical requirements include drawings, test procedures, or performance requirements); (ii) Critical product features/characteristics or specific acquisition concerns have been identified; and (iii) The contract is being awarded to— (A) A manufacturer or producer; or (B) A non-manufacturer or non-producer and specific Government verifications have been identified as necessary and feasible to perform. 3. Section 246.404 is added to read as follows: 246.404 Government contract quality assurance for acquisitions at or below the simplified acquisition threshold. Do not require Government contract quality assurance at source for contracts or delivery orders valued at or below the simplified acquisition threshold unless the criteria at 246.402 have been met. [FR Doc. 03-23341 Filed 9-12-03; 8:45 am]
Connectionstraces to 4
- 48 CFR 246
- 41 USC 421