§17-294. Southwest Power Pool — Regulatory and statutory framework

448 words·~2 min read·/ok/title-17-corporation-commission/17-294·

A research copy — for the controlling text, always check the official state or federal source. Not legal advice.

report.
A. The Corporation Commission shall coordinate with the regional transmission organization known as the Southwest Power Pool
(SPP)to develop and provide a reporting of the regulatory and statutory frameworks addressing the rule of the SPP as it pertains to this state. The report shall provide a comprehensive assessment of the impact of the SPP on the state’s electricity infrastructure and areas in which the state may desire further evaluation.
B. The report shall utilize the most recent twelve
(12)months of available data and shall include and consider the following:
1. An explanation of how decisions are made at the SPP, including the Regional State Committee (RSC), and the impact of such decisions on Oklahoma ratepayers;
2. The potential impact of decisions resulting from the SPP process, including the RSC, on the state budget;
3. The current use of intermittent power sources to meet baseload capacity requirements and explanation of the SPP’s decision-making processes regarding the use of these intermittent sources;
4. The studies and processes used by the SPP to assess and respond to demands, including transmission studies conducted;
5. Identification of SPP decisions and processes that may impact Oklahoma’s oil and natural gas industries;
6. Identification of areas in which Oklahoma stakeholders may benefit from additional information being shared on events occurring at the SPP;
7. The amount of power produced within Oklahoma that was transmitted outside of the state through the SPP for the calendar year ending December 31, 2023, the market value of such power, and any benefit of this transmission to Oklahoma ratepayers;
8. The cost, if any, that is built into the most recent rate cases with final orders previously before the Corporation Commission for the construction and maintenance of generation and transmission infrastructure which is used in whole or in part for the generation and transmission of power for sale outside of Oklahoma; and
9. An explanation of the level of input the Corporation Commission has on the processes and decisions of the SPP.
C. 1. The Commission shall ensure the completion of the report no later than December 31, 2024.
2. A copy of the finalized report shall be submitted electronically to the following:
a. the Governor,
b. the Speaker of the Oklahoma House of Representatives,
c. the President Pro Tempore of the Oklahoma State
Senate,
d. the Chair of the Utilities Committee of the House of
Representatives or successor committee,
e.
the Chair of the Energy and Telecommunications
Committee of the Senate or successor committee, and
f. the Chair of the Energy and Natural Resources
Committee of the House of Representatives or successor
committee. Added by Laws 2024, c. 288, § 1, emerg. eff. May 10, 2024.
★   the supreme law of the land   ★
Don't Tread on Me
E Pluribus Unum — out of many, one

"If you don't know your rights, you don't have any."

Marginalia · a citizen's law index
A research desk, not legal advice. Always read the cited source before relying on a summary.
Questions or an issue? support@self-law.org
disclaimerMarginalia is a research index, not a law firm. Nothing on this site is legal, tax, or financial advice and no attorney–client relationship is formed by using it. Statutes, regulations, and case law change; summaries, search results, AI output, and member posts may be incomplete, out of date, or wrong. Any interpretation drawn from material on this site should be validated by a licensed attorney in your jurisdiction before you act on it.