NRS 338.600 Withholding amounts for failure of subcontractor or supplier to comply with subcontract or applicable building code, law or regulation; payment of amounts withheld upon correction of condition.

327 words·~1 min read·/nv/chapter-338-public-works/338-600·

A research copy — for the controlling text, always check the official state or federal source. Not legal advice.

NRS 338.600 Withholding amounts for failure of subcontractor or supplier to comply with subcontract or applicable building code, law or regulation; payment of amounts withheld upon correction of condition.
1. Except as otherwise provided in NRS 338.595 , a subcontractor may withhold from a progress payment or retainage payment an amount sufficient to pay the expenses the subcontractor reasonably expects to incur as a result of the failure of his or her subcontractor or supplier to comply with the subcontract or applicable building code, law or regulation.
2. A subcontractor shall, within 10 days after the subcontractor receives:
(a)A progress payment or retainage payment from a contractor for an amount that is less than the amount set forth in the applicable progress bill or retainage bill; or
(b)A progress bill or retainage bill from his or her subcontractor or supplier,
Ê give a written notice to his or her subcontractor or supplier of any amount that will be withheld pursuant to this section.
3. The written notice must:
(a)Set forth:
(1)The amount of the progress payment or retainage payment that will be withheld from his or her subcontractor or supplier; and
(2)A detailed explanation of the reason the subcontractor will withhold that amount, including, without limitation, a specific reference to the provision or section of the subcontract, or documents related thereto, or applicable building code, law or regulation with which the subcontractor or supplier has failed to comply; and
(b)Be signed by an authorized agent of the subcontractor.
4. The subcontractor shall pay to his or her subcontractor or supplier the amount withheld by the public body, contractor or subcontractor within 10 days after:
(a)The subcontractor receives a written notice of the correction of the condition that is the reason for the withholding, signed by an authorized agent of his or her subcontractor or supplier; or
(b)The contractor pays to the subcontractor the amount withheld,
Ê whichever occurs later.
★   the supreme law of the land   ★
Don't Tread on Me
E Pluribus Unum — out of many, one

"If you don't know your rights, you don't have any."

Marginalia · a citizen's law index
A research desk, not legal advice. Always read the cited source before relying on a summary.
Questions or an issue? support@self-law.org
disclaimerMarginalia is a research index, not a law firm. Nothing on this site is legal, tax, or financial advice and no attorney–client relationship is formed by using it. Statutes, regulations, and case law change; summaries, search results, AI output, and member posts may be incomplete, out of date, or wrong. Any interpretation drawn from material on this site should be validated by a licensed attorney in your jurisdiction before you act on it.