NRS 108.225 Priority of liens.
137 words·~1 min read·
/nv/chapter-108-statutory-liens/108-225A research copy — for the controlling text, always check the official state or federal source. Not legal advice.
NRS 108.225 Priority of liens.
1. The liens provided for in NRS 108.221 to 108.246 , inclusive, are preferred to:
(a)Any lien, mortgage or other encumbrance which may have attached to the property after the commencement of construction of a work of improvement.
(b)Any lien, mortgage or other encumbrance of which the lien claimant had no notice and which was unrecorded against the property at the commencement of construction of a work of improvement.
2. Every mortgage or encumbrance imposed upon, or conveyance made of, property affected by the liens provided for in NRS 108.221 to 108.246 , inclusive, after the commencement of construction of a work of improvement are subordinate and subject to the liens provided for in NRS 108.221 to 108.246 , inclusive, regardless of the date of recording the notices of liens.