58:11-9.6. Renewal of permit, prerequisites to
109 words·~1 min read·
/nj/title-58/chapter-11/58-11-9-6·A research copy — for the controlling text, always check the official state or federal source. Not legal advice.
The State department, before it renews any permit, shall be satisfied of the following facts:
(a)That the approved physical connection has been tested for tightness under prevailing pressure conditions at least every 3 months;
(b)That the approved physical connection has been subjected to an internal inspection within 6 months prior to the application; and
(c)That the local board of health, the State department, and the owner of the water supply set forth in section 3 of this act, have determined that the approved physical connection was functioning satisfactorily.
L.1942, c. 308, p. 1141, s. 6. Amended by L.1966, c. 47, s. 5, eff. May 24, 1966.