76-3307. Pipeline carrier; reclamation actions required within thirty days; exception.
43 words·~1 min read·
/ne/chapter-76/76-3307A research copy — for the controlling text, always check the official state or federal source. Not legal advice.
A pipeline carrier shall complete final grading, topsoil replacement, installation of erosion control structures, seeding, and mulching within thirty days after backfill except when weather conditions, extenuating circumstances, or unforeseen developments do not permit the work to be done within such thirty-day period.