75-134. Commission order; requirements; when effective; rate order under State Natural Gas Regulation Act; appeal; stay enforcement.

351 words·~2 min read·/ne/chapter-75/75-134

A research copy — for the controlling text, always check the official state or federal source. Not legal advice.

(1)A commission order entered after a hearing shall be written and shall recite
(a)a discussion of the facts of a basic or underlying nature,
(b)the ultimate facts, and
(c)the commission's reasoning or other authority relied upon by the commission.
(2)Every order of the commission shall become effective ten days after the date of the mailing of a copy of the order to the parties of record except
(a)when the commission prescribes an alternate effective date,
(b)as otherwise provided in section 75-121 or 75-139 ,
(c)for cease and desist orders issued pursuant to section 75-133 which shall become effective on the date of entry, or
(d)for orders entered pursuant to section 75-319 which shall become effective on the date of entry.
(3)Except as otherwise provided in this section or for rate orders provided for in section 75-139 , any appeal of a commission order shall not stay enforcement of such order unless otherwise ordered by the commission or the Court of Appeals.
(4)Notwithstanding subsection
(3)of this section, any appeal of a rate order under the State Natural Gas Regulation Act entered pursuant to section 66-1838 shall stay enforcement of such order pending resolution of the appeal.
The "reasoning" requirement of this section is satisfied by a Public Service Commission order containing a statement of underlying facts, ultimate facts, and findings where the issues involved are issues of fact. Hugelman v. A & A Trucking, Inc., 198 Neb. 628, 254 N.W.2d 412 (1977).
The filing of a motion for rehearing before the Public Service Commission is the commencement of an appeal proceeding, and where followed by overruling of the motion and filing of notice of appeal and appeal to Supreme Court the rate order is put in abeyance until a supersedeas bond is filed. Chicago & Northwestern Transp. Co. v. Nebco, Inc., 196 Neb. 490, 243 N.W.2d 779 (1976).
An order of Railway Commission which fails to make findings of ultimate facts will be set aside on appeal. Andrews Van Lines, Inc. v. Smith, 187 Neb. 533, 192 N.W.2d 406 (1971).
★   the supreme law of the land   ★
Don't Tread on Me
E Pluribus Unum — out of many, one

"If you don't know your rights, you don't have any."

Marginalia · a citizen's law index
A research desk, not legal advice. Always read the cited source before relying on a summary.
Questions or an issue? support@self-law.org
disclaimerMarginalia is a research index, not a law firm. Nothing on this site is legal, tax, or financial advice and no attorney–client relationship is formed by using it. Statutes, regulations, and case law change; summaries, search results, AI output, and member posts may be incomplete, out of date, or wrong. Any interpretation drawn from material on this site should be validated by a licensed attorney in your jurisdiction before you act on it.