70-626.02. Generating power agency; physical connections; establish; rates.

104 words·~1 min read·/ne/chapter-70/70-626-02

A research copy — for the controlling text, always check the official state or federal source. Not legal advice.

A generating power agency shall establish a physical connection of its transmission lines and associated facilities with the facilities of a distribution power agency or with the facilities of an intervening power agency when requested by the distribution power agency and shall make available any surplus capacity in its transmission lines and associated facilities and provide for the receipt, transmission, and delivery of power and energy for the account of the distribution power agency upon the payment of rates, tolls, and charges that are reasonable, fair, and nondiscriminatory for the use made of the transmission lines and associated facilities of the generating power agency.
★   the supreme law of the land   ★
Don't Tread on Me
E Pluribus Unum — out of many, one

"If you don't know your rights, you don't have any."

Marginalia · a citizen's law index
A research desk, not legal advice. Always read the cited source before relying on a summary.
Questions or an issue? support@self-law.org
disclaimerMarginalia is a research index, not a law firm. Nothing on this site is legal, tax, or financial advice and no attorney–client relationship is formed by using it. Statutes, regulations, and case law change; summaries, search results, AI output, and member posts may be incomplete, out of date, or wrong. Any interpretation drawn from material on this site should be validated by a licensed attorney in your jurisdiction before you act on it.