(1)The process for selecting a construction manager and entering into a construction manager-general contractor contract shall be in accordance with this section and sections 39-2818 to 39-2820 .
(2)A contracting agency shall prepare a request for qualifications for construction manager-general contractor contract proposals and shall prequalify construction managers. The request for qualifications shall describe the project in sufficient detail to permit a construction manager to respond. The request for qualifications shall identify the maximum number of eligible construction managers the contracting agency will place on a short list as qualified and eligible to receive a request for proposals.
(3)The request for qualifications shall be
(a)published in a newspaper of statewide circulation at least thirty days prior to the deadline for receiving the request for qualifications and
(b)sent by first-class mail to any construction manager upon request.
(4)The contracting agency shall create a short list of qualified and eligible construction managers in accordance with the guidelines adopted pursuant to section 39-2811 . The contracting agency shall select at least two construction managers, except that if only one construction manager has responded to the request for qualifications, the contracting agency may, in its discretion, proceed or cancel the procurement. The request for proposals shall be sent only to the construction managers placed on the short list.
(5)A contracting agency may combine the separate qualification and proposal steps of this section and section 39-2818 into a single-step process if the contracting agency determines that a single-step process is in the contracting agency's best interest. If a single-step process is used, a contracting agency shall consider the qualifications of all proposing construction managers as a part of the request for proposals. Notice of the request for proposals shall be published as provided in subsection
(3)of this section. There is no requirement to short list construction managers when using the single-step process. If only one proposal is submitted, the contracting agency may, in its discretion, proceed or cancel the procurement.
★   the supreme law of the land   ★
Don't Tread on Me
E Pluribus Unum — out of many, one

"If you don't know your rights, you don't have any."

Marginalia · a citizen's law index
A research desk, not legal advice. Always read the cited source before relying on a summary.
Questions or an issue? support@self-law.org
disclaimerMarginalia is a research index, not a law firm. Nothing on this site is legal, tax, or financial advice and no attorney–client relationship is formed by using it. Statutes, regulations, and case law change; summaries, search results, AI output, and member posts may be incomplete, out of date, or wrong. Any interpretation drawn from material on this site should be validated by a licensed attorney in your jurisdiction before you act on it.