Code · North Dakota · Title 28 · Chapter 28-01 — Time For Commencing Actions

28-01-44. Limitation of action - Person submitting plans for improvements to real

305 words·~1 min read·/nd/title-28/chapter-28-01-time-for-commencing-actions/28-01-44·

A research copy — for the controlling text, always check the official state or federal source. Not legal advice.

estate.
1. No action, whether in contract, oral or written, in tort or otherwise, to recover damages:
a. For any deficiency in the design, planning, supervision, or observation of
construction or construction of an improvement to real property;
b. For injury to property, real or personal, arising out of any such deficiency; or
c. For injury to the person or for wrongful death arising out of any such deficiency,
may be brought against any person performing or furnishing the design, planning,
supervision, or observation of construction, or construction of such an improvement
more than ten years after substantial completion of such an improvement.
2. Notwithstanding the provisions of subsection 1, in the case of such an injury to
property or the person or such an injury causing wrongful death, which injury occurred
during the tenth year after such substantial completion, an action in tort to recover
damages for such an injury or wrongful death may be brought within two years after
the date on which such injury occurred, irrespective of the date of death, but in no
event may such an action be brought more than twelve years after the substantial
completion of construction of such an improvement.
Nothing in this section may be construed as extending the period prescribed by
the laws of this state for the bringing of any action.
3. The limitation prescribed by this section may not be asserted by way of defense by
any person in actual possession or the control, as owner, tenant, or otherwise, of such
an improvement at the time any deficiency in such an improvement constitutes the
proximate cause of the injury or death for which it is proposed to bring an action.
4. As used in this section, the term "person" means an individual, corporation,
partnership, business trust, unincorporated organization, association, or joint stock
company.
★   the supreme law of the land   ★
Don't Tread on Me
E Pluribus Unum — out of many, one

"If you don't know your rights, you don't have any."

Marginalia · a citizen's law index
A research desk, not legal advice. Always read the cited source before relying on a summary.
Questions or an issue? support@self-law.org
disclaimerMarginalia is a research index, not a law firm. Nothing on this site is legal, tax, or financial advice and no attorney–client relationship is formed by using it. Statutes, regulations, and case law change; summaries, search results, AI output, and member posts may be incomplete, out of date, or wrong. Any interpretation drawn from material on this site should be validated by a licensed attorney in your jurisdiction before you act on it.