§ 62-182. Acquisition of right-of-way by contract.
122 words·~1 min read·
/nc/chapter-62/62-182A research copy — for the controlling text, always check the official state or federal source. Not legal advice.
§ 62-182. Acquisition of right-of-way by contract.
Such telegraph, telephone, or electric power or lighting company has power to contract with any person or corporation, the owner of any lands or of any franchise or easement therein, over which its lines are proposed to be erected, for the right-of-way for planting, repairing and preservation of its poles or other property, and for the erection and occupation of offices at suitable distances for the public accommodation. This section shall not be construed as requiring electric power or lighting companies to erect offices for public accommodation. (1874-5, c. 203, s. 3; Code, s. 2008; 1899, c. 64; 1903, c. 562, ss. 1, 2; Rev., s. 1572; C.S., s. 1697; 1963, c. 1165, s. 1.)