82-4-121. Permit required.
59 words·~1 min read·
/mt/title-82/chapter-4/part-1/82-4-121A research copy — for the controlling text, always check the official state or federal source. Not legal advice.
82-4-121 . Permit required. No person may commence preparatory work until the operator shall have first obtained from the department a mine-site location permit for a new strip mine or a new underground mine or a permit under part 2 of this chapter, if the application for such permit includes an appropriate long-range mining plan acceptable to the department.