75-26-402 . (Effective January 1, 2026) Required setback for wind turbine generators. After January 1, 2026, a wind turbine generator built pursuant to a wind energy agreement as described in 70-17-406 may not be constructed if the wind turbine tower is 500 feet or more in height, as measured from the natural ground level at the base of the tower to the tip of the turbine rotor blade, if the base of the tower is located at a distance of less than 1,500 feet from an occupied residence, unless a shorter setback distance is approved by the owner of the real property.
★   the supreme law of the land   ★
Don't Tread on Me
E Pluribus Unum — out of many, one

"If you don't know your rights, you don't have any."

Marginalia · a citizen's law index
A research desk, not legal advice. Always read the cited source before relying on a summary.
Questions or an issue? support@self-law.org
disclaimerMarginalia is a research index, not a law firm. Nothing on this site is legal, tax, or financial advice and no attorney–client relationship is formed by using it. Statutes, regulations, and case law change; summaries, search results, AI output, and member posts may be incomplete, out of date, or wrong. Any interpretation drawn from material on this site should be validated by a licensed attorney in your jurisdiction before you act on it.