75-20-231. Expedited review.
100 words·~1 min read·
/mt/title-75/chapter-20/part-2/75-20-231A research copy — for the controlling text, always check the official state or federal source. Not legal advice.
75-20-231 . Expedited review.
(1)Except as provided in 75-1-208 (4)(b), the department shall issue a certification decision within 90 days from the date on which an application is considered complete for a facility that:
(a)is unlikely to result in significant adverse environmental impacts based on the criteria listed in 75-20-232 ; or
(b)is presently in existence and proposed for upgrade, reconstruction, or relocation and is unlikely to result in significant impacts pursuant to 75-20-232 .
(2)A facility that qualifies for expedited review is exempt from undergoing an alternative siting study, except as provided in 75-1-201 .