69-4-1003. Advanced metering devices -- notice required.
129 words·~1 min read·
/mt/title-69/chapter-4/part-10/69-4-1003·A research copy — for the controlling text, always check the official state or federal source. Not legal advice.
69-4-1003 . Advanced metering devices -- notice required.
(1)A utility shall:
(a)notify a customer in writing at least 60 days prior to installation of an advanced metering device at the customer's address; and
(b)provide a sample copy of the notice to the public service commission and a list of customers who have been provided notice.
(2)The notice provided in accordance with subsection
(1)must:
(a)be sent by first-class mail to a customer's address and be separate from any billing mailing;
(b)clearly state the utility's intent to install an advanced metering device; and
(c)if determined to be a requirement by the public service commission, include the process and financial obligations for a customer to opt out of installation of an advanced metering device.