69-3-714. Criteria for allowable advanced conductor programs.
117 words·~1 min read·
/mt/title-69/chapter-3/part-7/69-3-714A research copy — for the controlling text, always check the official state or federal source. Not legal advice.
69-3-714 . Criteria for allowable advanced conductor programs.
(1)The commission may approve cost-effectiveness criteria for advanced conductor projects that may be placed into a utility's rate base under this part.
(2)Criteria must be based on established direct current resistance at standard pressure and a temperature of 20 degrees Celsius.
(3)As used in this section, "advanced conductor" means an overhead electricity conductor installed in a transmission or distribution project that has a direct current electrical resistance at least 10% lower than existing conductors of a similar diameter on the system.
(4)In establishing cost-effectiveness criteria, the commission may consider decreased electrical losses and any other relevant consumer, environmental, and system benefits provided by advanced conductors.