69-3-1204. Integrated least-cost plan.

573 words·~3 min read·/mt/title-69/chapter-3/part-12/69-3-1204·

A research copy — for the controlling text, always check the official state or federal source. Not legal advice.

69-3-1204 . Integrated least-cost plan.
(a)The commission shall adopt rules requiring a public utility to prepare and file a plan at least every 3 years for meeting the requirements of its customers in the most cost-effective manner consistent with the public utility's obligation to serve and in accordance with this part.
(b)The rules must prescribe the content and the time for filing a plan.
(a)A plan must contain but is not limited to:
(i)an evaluation of the full range of cost-effective means for the public utility to meet the service requirements of its Montana customers, including conservation or similar improvements in the efficiency by which services are used and including demand-side management programs in accordance with 69-3-1209 ;
(ii)an annual electric demand and energy forecast developed pursuant to commission rules that includes energy and demand forecasts for each year within the planning period and historical data, as required by commission rule;
(iii)an assessment of planning reserve margins and contingency plans for the acquisition of additional resources developed pursuant to commission rules;
(iv)an assessment of the need for additional resources and the utility's plan for acquiring resources;
(v)the proposed process the utility intends to use to solicit bids for energy and capacity resources to be acquired through a competitive solicitation process in accordance with 69-3-1207 ; and
(vi)descriptions of at least two alternate scenarios that can be used to represent the costs and benefits from increasing amounts of renewable energy resources and demand-side management programs, based on rules developed by the commission.
(b)The utility shall fully explain, justify, and document the data, assumptions, methodologies, models, determinants, and any other inputs on which it relied to develop information required in subsection (2)(a).
(a)The commission may adopt rules providing guidelines to be used in preparing a plan and identifying the criteria to be used in determining cost-effectiveness.
(b)The criteria may include externalities associated with the acquisition of a resource by a public utility.
(c)The rules must establish the minimum filing requirements for acceptance of a plan by the commission for further review. If a plan does not meet the minimum filing requirements, it must be returned to the public utility with a list of filing requirements not met. A corrected plan must be submitted within the time established by the commission.
(4)A plan filed with the commission by a utility, as defined in 75-20-104 , must be provided to the department of environmental quality and the consumer counsel.
(5)Within 120 days of receipt of a complete plan, the commission:
(a)shall review the plan;
(b)shall publish a copy of the plan;
(c)shall allow for a minimum of 60 days for the public to comment on the plan; and
(d)shall provide public meetings in accordance with 69-3-1205 .
(a)The commission may identify deficiencies in the plan, including:
(i)any concerns of the commission regarding the public utility's compliance with commission rules; and
(ii)ways to remedy the concerns.
(b)The commission may engage independent engineering, financial, and management consultants or advisory services to evaluate a public utility's plan. The consultants shall demonstrate knowledge and experience with resource procurement and resource portfolio management, modeling, risk management, and engineering practices. The commission shall charge a fee to the public utility to pay for the costs of consultants or advisory services. These costs are recoverable in rates.
★   the supreme law of the land   ★
Don't Tread on Me
E Pluribus Unum — out of many, one

"If you don't know your rights, you don't have any."

Marginalia · a citizen's law index
A research desk, not legal advice. Always read the cited source before relying on a summary.
Questions or an issue? support@self-law.org
disclaimerMarginalia is a research index, not a law firm. Nothing on this site is legal, tax, or financial advice and no attorney–client relationship is formed by using it. Statutes, regulations, and case law change; summaries, search results, AI output, and member posts may be incomplete, out of date, or wrong. Any interpretation drawn from material on this site should be validated by a licensed attorney in your jurisdiction before you act on it.