319.025. Excavator must give notice and obtain information, when, how — notice to notification center, when — clarification of markings, response — permit for highway excavation required. — 1. Except as provided in subsection 4 of section 319.030 and in section 319.050 , an excavator shall not make or begin any excavation in any public street, road or alley, right-of-way dedicated to the public use or utility easement of record or within any private street or private property until such excavator gives notice to the notification center and obtains information concerning the possible location of any underground facilities which may be affected by said excavation from underground facility owners whose names appear on the current list of participants in the notification center and who were communicated to the excavator as notification center participants who would be informed of the excavation notice.
Notice to the notification center of proposed excavation shall be deemed notice to all owners and operators of underground facilities and shall have an operational life ending at 11:59 p.m. twenty-one consecutive calendar days from the start date of work. The notice referred to in this section shall comply with the provisions of section 319.026 .
2. An excavator's notice to owners and operators of underground facilities participating in the notification center pursuant to section 319.022 is ineffective for purposes of subsection 1 of this section unless given to such notification center.
3. Notification center participants shall be relieved of the responsibility to respond to a notice of intent to excavate received directly from the person intending to commence an excavation, except for requests for clarification of markings through on-site meetings as provided in subsection 1 of section 319.030 and requests for locations at the time of an emergency as provided by section 319.050 .
4. Notwithstanding the provisions of this section to the contrary, a person shall not make or begin any excavation in any state highway, or on the right-of-way of any state highway, without first obtaining a permit from the state highways and transportation commission pursuant to section 227.240 , provided however, the provisions of this subsection shall not apply to railroad right-of-way owned or operated by a railroad.
­­--------
(L. 1976 S.B. 583 § 4, A.L. 1991 S.B. 214 & 264, A.L. 2001 H.B. 425, A.L. 2008 H.B. 1779, A.L. 2011 S.B. 173, A.L. 2014 H.B. 1867, A.L. 2025 S.B. 133)
★   the supreme law of the land   ★
Don't Tread on Me
E Pluribus Unum — out of many, one

"If you don't know your rights, you don't have any."

Marginalia · a citizen's law index
A research desk, not legal advice. Always read the cited source before relying on a summary.
Questions or an issue? support@self-law.org
disclaimerMarginalia is a research index, not a law firm. Nothing on this site is legal, tax, or financial advice and no attorney–client relationship is formed by using it. Statutes, regulations, and case law change; summaries, search results, AI output, and member posts may be incomplete, out of date, or wrong. Any interpretation drawn from material on this site should be validated by a licensed attorney in your jurisdiction before you act on it.