216B.72 QUALIFIED LARGE-SCALE DATA CENTER FEE.
133 words·~1 min read·
/mn/chapter-216/216b-72A research copy — for the controlling text, always check the official state or federal source. Not legal advice.
216B.72 QUALIFIED LARGE-SCALE DATA CENTER FEE.
(a)The commissioner must collect an annual fee from the qualified large-scale data center, on a schedule prescribed by the commissioner and deposited in the energy and conservation account established in section 216B.241, subdivision 2a .
(b)The fee is based on the qualified large-scale data center's peak demand the utility arranges to serve, reflecting the qualified large-scale data center's peak demand forecast provided to the utility, expressed in megawatts (MW), as follows:
Peak Demand Fee
(1)100 to 250 MW $2,000,000
(2)above 250 MW but below 500 MW $3,000,000
(3)500 MW but below 750 MW $4,000,000
(4)750 MW or greater $5,000,000
(c)The fee data collected under this section must be treated as nonpublic data, as defined under section 13.02, subdivision 9 .