161.3414 DETERMINATION TO USE DESIGN-BUILD SELECTION METHOD.
§
Subdivision 1. General criteria.
A design-build contracting procedure authorized under sections 161.3410 to 161.3426 may be used for a specific project only after the commissioner determines that awarding a design-build contract will serve the public interest.
§
Subd. 2. Specific criteria.
The commissioner shall use the following criteria as the minimum basis for determining when to use the design-build method of project delivery:
(1)the extent to which it can adequately define the project requirements in a proposed scope of the design and construction desired;
(2)the time constraints for delivery of the project;
(3)the capability and experience of potential contractors with the design-build method of project delivery or similar experience;
(4)the suitability of the project for use of the design-build method of project delivery with respect to time, schedule, costs, and quality factors;
(5)the capability of the Department of Transportation to manage the project, including the employment of experienced personnel or outside consultants;
(6)the capability of the Department of Transportation to oversee the project with individuals or design-build firms who are familiar and experienced with the design-build method of project delivery or similar experience;
(7)the lack of ability and availability of any current state employee to perform the services called for by the contract;
(8)the original character of the product or the services;
(9)the work to be performed on the project is necessary to the agency's achievement of its statutory responsibilities and there is statutory authority to enter into the contract; and
(10)other criteria the commissioner deems relevant and states in writing in its determination to utilize the design-build method of project delivery.
★   the supreme law of the land   ★
Don't Tread on Me
E Pluribus Unum — out of many, one

"If you don't know your rights, you don't have any."

Marginalia · a citizen's law index
A research desk, not legal advice. Always read the cited source before relying on a summary.
Questions or an issue? support@self-law.org
disclaimerMarginalia is a research index, not a law firm. Nothing on this site is legal, tax, or financial advice and no attorney–client relationship is formed by using it. Statutes, regulations, and case law change; summaries, search results, AI output, and member posts may be incomplete, out of date, or wrong. Any interpretation drawn from material on this site should be validated by a licensed attorney in your jurisdiction before you act on it.