460.1321 Municipally owned electric utility; collocation on nonauthority poles; standards; application process; moratorium prohibited; rates; make-ready work.

564 words·~3 min read·/mi/chapter-460/460-1321

A research copy — for the controlling text, always check the official state or federal source. Not legal advice.

460.1321 Municipally owned electric utility; collocation on nonauthority poles; standards; application process; moratorium prohibited; rates; make-ready work.
Sec. 21.
(1)The governing body of a municipally owned electric utility shall not enter into an exclusive arrangement with any person for the right to attach to nonauthority poles.
(2)The governing body of a municipally owned electric utility shall allow the collocation of small cell wireless facilities on nonauthority poles on a nondiscriminatory basis.
(3)The collocation of small cell wireless facilities on nonauthority poles by a wireless provider shall comply with the applicable, nondiscriminatory safety and reliability standards adopted by the governing body of a municipally owned electric utility and with the "National Electric Safety Code" published by the Institute of Electrical and Electronics Engineers. The governing body of a municipally owned electric utility may require a wireless provider to execute an agreement for nonauthority pole attachments if such an agreement is required of all other nonauthority pole attachments.
(4)The governing body of a municipally owned electric utility shall adopt a process for requests by wireless providers to colocate small cell wireless facilities on nonauthority poles that is nondiscriminatory and competitively neutral. If such a process has not been adopted within 90 days after the effective date of this act, the application process in section 15 applies to such requests. The governing body of a municipally owned electric utility shall not impose a moratorium on the processing of nonauthority pole collocation requests, or require a wireless provider to perform any service not directly related to the collocation. The governing body of a municipally owned electric utility may charge a fee not to exceed $100.00 per nonauthority pole for processing the request. The governing body of a municipally owned electric utility may charge an additional fee not to exceed $100.00 per nonauthority pole for processing the request, if a modification or maintenance of the collocation requires an engineering analysis. Every 5 years after the effective date of this act, the maximum fees then authorized under this subsection are increased by 10% and rounded to the nearest dollar.
(5)The rate for a wireless provider to colocate on a nonauthority pole in the ROW shall not exceed $50.00 annually per nonauthority pole. Every 5 years after the effective date of this act, the maximum rate then authorized under this subsection is increased by 10% and rounded to the nearest dollar.
(6)A wireless provider shall comply with the process for make-ready work that the governing body of a municipally owned electric utility has adopted for other parties under the same or similar circumstances that attach facilities to nonauthority poles. If such a process has not been adopted, the wireless provider and the governing body of a municipally owned electric utility shall comply with the process for make-ready work under 47 USC 224 and implementing orders and regulations. A good-faith estimate established by the governing body of a municipally owned electric utility for any make-ready work for nonauthority poles shall include pole replacement if necessary. All make-ready costs shall be based on actual costs, with detailed documentation provided.
(7)If a wireless provider is required to relocate small cell wireless facilities colocated on a nonauthority pole, it shall do so in accordance with the nondiscriminatory terms adopted by the governing body of a municipally owned electric utility.
History: 2018, Act 365 , Eff. Mar. 12, 2019
★   the supreme law of the land   ★
Don't Tread on Me
E Pluribus Unum — out of many, one

"If you don't know your rights, you don't have any."

Marginalia · a citizen's law index
A research desk, not legal advice. Always read the cited source before relying on a summary.
Questions or an issue? support@self-law.org
disclaimerMarginalia is a research index, not a law firm. Nothing on this site is legal, tax, or financial advice and no attorney–client relationship is formed by using it. Statutes, regulations, and case law change; summaries, search results, AI output, and member posts may be incomplete, out of date, or wrong. Any interpretation drawn from material on this site should be validated by a licensed attorney in your jurisdiction before you act on it.