324.63522 Determination of probable hydrologic consequences and statement of boring or sampling results; performance; cost.
118 words·~1 min read·
/mi/chapter-324/324-63522A research copy — for the controlling text, always check the official state or federal source. Not legal advice.
324.63522 Determination of probable hydrologic consequences and statement of boring or sampling results; performance; cost.
Sec. 63522.
If the department finds that the probable total annual production at all locations of a surface coal mining operator will not exceed 100,000 tons, the determination of probable hydrologic consequences and statement of the results of test borings or core samplings required by section 63516, on the written request of the operator, shall be performed by a qualified governmental agency or private consultant designated by the department, and the cost of the preparation of the determination and statement shall be assumed by the department.
History: Add. 1995, Act 57, Imd. Eff. May 24, 1995
Popular Name: Act 451
Popular Name: NREPA