§ 9-698
339 words·~2 min read·
/md/environment/9-698A research copy — for the controlling text, always check the official state or federal source. Not legal advice.
§9–698.
(a)Before a person may dig in or do any other construction on any way in a service area, the person shall obtain from the sanitary commission approval of the digging or construction.
(b)To obtain approval, the person shall file with the sanitary commission a plan for the digging or construction that shows the depth and location of each:
(1)Conduit;
(2)Main;
(3)Pipe;
(4)Pole; and
(5)Other structure.
(c)If approval of the plans has been obtained from the sanitary commission, before a person may do any digging or construction different from the approved plans, the person shall:
(1)Submit a new plan that shows the changes in the information required for the original plan; and
(2)Obtain approval from the sanitary commission to do the digging or construction according to the new plan.
(d)If any obstruction has been constructed in, on, or under a way in violation of this section and if the sanitary commission is required to move that obstruction to build or operate a project:
(1)The district may move the obstruction and charge the cost of moving the obstruction to:
(i)The person who constructed or installed the obstruction; or
(ii)Any successor in interest to that person;
(2)The owner of the obstruction is not entitled to compensation under this subtitle for moving the obstruction; and
(3)The district is not liable for damage done to the obstruction.
(e)Before beginning work on the plumbing system on any property in a service area, a person shall:
(1)Obtain from the district a permit to do the plumbing work;
(2)Pay to the district the permit fee that the sanitary commission requires; and
(3)Allow the sanitary commission to inspect the plumbing work.
(f)Before connecting the plumbing system of any property to a water pipe or sewer pipe operated by the district, a person shall:
(1)Obtain from the district a permit to make the connection; and
(2)Comply with any additional conditions that the sanitary commission requires.