§ 7-408
95 words·~1 min read·
/md/environment/7-408A research copy — for the controlling text, always check the official state or federal source. Not legal advice.
§7–408.
(a)A certificate automatically shall be null and void if:
(1)Construction or other preparation of the site for its intended use of the facility for which the certificate was issued has not commenced within 2 years following issuance of the certificate; or
(2)The facility has not commenced operation within 4 years following issuance of the certificate.
(b)The Board may extend the time limits imposed under subsection
(a)of this section if the certificate holder:
(1)Applies to the Board for an extension; and
(2)Shows good cause for allowing the extension.