RS 38:2291
112 words·~1 min read·
/la/title-38/38-438A research copy — for the controlling text, always check the official state or federal source. Not legal advice.
RS 38:2291
§2291. Written notice to approving authority of inclusion of closed specification
Whenever an architect or engineer, either directly or indirectly, has included a closed specification in the specifications for a public building or project, he shall submit a written report to the building authority, ten days prior to the final submission of specifications, which report shall include the following:
(1)Identification of each closed specification;
(2)A concise statement of the reasons for including a closed specification;
(3)Identification of other products which are apparently equal and a concise statement as to why they may be excluded under the provisions of R.S. 38:2290.
Added by Acts 1965, No. 40, §1.