45A.260 Limitations on claims.
103 words·~1 min read·
/ky/chapter-45a/45a-260A research copy — for the controlling text, always check the official state or federal source. Not legal advice.
(1)Any claim arising from a construction contract executed and administered by the
Transportation Cabinet pursuant to the provisions of KRS Chapters 175, 176, 177
and 180 shall be commenced in Franklin Circuit Court within one
(1)year from the
time the Commonwealth has determined final pay quantities and issues a final pay
estimate to the contracting party, notifying him of its final determination, or from
the receipt of a final adverse decision from the Commonwealth, whichever occurs
later.
(2)Any other claim shall be commenced in Franklin Circuit Court within one
(1)year
from the date of completion specified in the contract.