350.455 Water impoundment on mining site.
179 words·~1 min read·
/ky/chapter-350/350-455A research copy — for the controlling text, always check the official state or federal source. Not legal advice.
If authorized in the approved mining and reclamation plan and permit, the permittee or operator may create permanent impoundments of water on mining sites as part of reclamation activities only when it is adequately demonstrated that:
(1)The size of the impoundment is adequate for its intended purposes;
(2)The impoundment dam construction will be so designed as to achieve necessary
stability with an adequate margin of safety compatible with that of structures
constructed under Public Law 83-566 (16 U.S.C. 1006);
(3)The quality of impounded water will be suitable on a permanent basis for its
intended use and that discharges from the impoundment will not degrade the water
quality below water quality standards established pursuant to applicable federal and
state law in the receiving stream;
(4)The level of water will be reasonably stable;
(5)Final grading will provide adequate safety and access for proposed water users; and
(6)The water impoundments will not result in the diminution of the quality or quantity
of water utilized by adjacent or surrounding landowners for agricultural, industrial,