278.212 Filing of plans for electrical interconnection with merchant electric

116 words·~1 min read·/ky/278-212

A research copy — for the controlling text, always check the official state or federal source. Not legal advice.

generating facility -- Costs of upgrading existing grid.
(1)No utility shall begin the construction or installation of any property, equipment, or
facility to establish an electrical interconnection with a merchant electric generating
facility in excess of ten megawatts
(10MW)until the plans and specifications for
the electrical interconnection have been filed with the commission.
(2)Notwithstanding any other provision of law, any costs or expenses associated with
upgrading the existing electricity transmission grid, as a result of the additional load
caused by a merchant electric generating facility, shall be borne solely by the person
constructing the merchant electric generating facility and shall in no way be borne
by the retail electric customers of the Commonwealth.
★   the supreme law of the land   ★
Don't Tread on Me
E Pluribus Unum — out of many, one

"If you don't know your rights, you don't have any."

Marginalia · a citizen's law index
A research desk, not legal advice. Always read the cited source before relying on a summary.
Questions or an issue? support@self-law.org
disclaimerMarginalia is a research index, not a law firm. Nothing on this site is legal, tax, or financial advice and no attorney–client relationship is formed by using it. Statutes, regulations, and case law change; summaries, search results, AI output, and member posts may be incomplete, out of date, or wrong. Any interpretation drawn from material on this site should be validated by a licensed attorney in your jurisdiction before you act on it.